Nova Minerals has the final state approvals for its Alaska antimony project and the company is targeting production in 2027.

What starts in 2027 is a pilot plant sized to a Department of War award, and Nova has yet to publish an assay for the trisulfide it plans to make.

On 27 October 2026 Nova Minerals Corp (NYSE American: NVA, ASX: NVA) said the Alaska Department of Natural Resources had approved the plan of operations and reclamation plan for its antimony project, completing its permitting. The announcement was lodged with the ASX on 28 October. The approvals authorise construction and operations for an initial three-year term across three sites:

  • stibnite mining at the Styx and Stibium prospects on the Estelle project.

  • ore sorting and processing at the Whiskey Bravo concentration site, also within Estelle.

  • processing and refining at Port MacKenzie.

The permits came through about three months after submission, according to Nova. Its field-season update of 12 August 2026 reported the plan as submitted for final review.

The project is paid for by a $43.4m Defense Production Act Title III award, made in October 2025 to Alaska Range Resources, Nova's US subsidiary. Nova filed its annual report with the SEC on 30 September 2026. The report describes the award as a 24-month firm fixed-price sub-agreement, awarded through the Defense Industrial Base Consortium. Its purpose is a pilot-scale plant capable of producing military-grade antimony trisulfide. The government may modify or terminate the award. Nova describes the award as fully funding Phase 1. The major long-lead equipment has been bought and delivered, including about 500 tons of processing and refining equipment for the plant, which reached Port MacKenzie by barge in early September 2026.

Nova's 2027 production target is for that plant. The annual report says the first trisulfide output will meet the award's requirements and is not expected to bring in material revenue in the year to 30 June 2027. Nova has no mineral resource estimate for antimony at Estelle; its defined resources are gold. A commercial-scale antimony operation would depend on further government grants or other funding. The report's risk factors also state substantial doubt about Nova's ability to continue as a going concern.

Process plant engineering and metallurgical testwork are complete, the company says. Its flowsheet is designed for two products: military-grade trisulfide, and standard grade II antimony metal above 99.65 per cent antimony, which matches the minimum for Regulus II, a commercial grade. Antimony metal has civilian and military uses alike, from storage batteries and bearings to ordnance. The military specification for trisulfide is MIL-DTL-159E, issued on 12 September 2023. It requires:

  • at least 70.5 per cent antimony;

  • no more than 0.15 per cent lead and 0.06 per cent arsenic;

  • testing of every lot, plus first article inspection where a contract calls for it.

The announcement names no specification for the trisulfide. In May 2026 Nova said it had made military-grade trisulfide at laboratory scale and that the material was being assayed and certified. On 12 August it said samples had been submitted for independent analysis. This publication has found no results published since.

Next, Nova has to build and operate the Port MacKenzie plant and have its trisulfide qualified.

The permits allow the first of those steps to begin. On 8 October Nova said construction at Port MacKenzie would start once they arrived, and early earthworks were already under way.