Europe's best-known antimony prospect has four more years to explore and no timetable to mine. It is also the kind of project that would test the case for a strategic antimony project should the EU add antimony to the strategic mineral list in addition to the critical mineral list.
Military Metals (CSE: MILI; OTCQB: MILIF) announced on 19 October 2026 that the Slovak authorities had reinstated the Trojárová exploration licence and extended it by four years. The Ministry of the Environment cancelled the licence on 28 May 2026 after an unscheduled review. The company appealed to the Minister of the Environment. It says it received the Ministry's decision annulling the cancellation on 2 October, reinstating the licence to 18 October 2026, and that the authority also issued the four-year extension.
The Ministry of the Environment began proceedings to cancel the exploration area on its own initiative in December 2025, after the municipalities of Pezinok and Pernek launched a petition in May 2025 over risks to drinking water and protected areas. Its 28 May 2026 decision, under Minister Tomáš Taraba, held that the area's continued existence was contrary to the public interest, notably protection of the environment and residents' health. Military Metals countered that the Ministry had itself listed Trojárová as a critical-raw-materials exploration area on 20 February 2025. On 19 October the Ministry told the news agency TASR that it had annulled the cancellation for unlawfulness, that the company had met all conditions for the four-year extension, and that following the rules on exploration areas had spared Slovakia a €200 million arbitration. Any mining would still need an environmental assessment and approvals under mining law, which fall to the Ministry of Economy.
Trojárová, near Pezinok, about 20 km northeast of Bratislava, holds an inferred resource of 6.5 million tonnes at 1.02% antimony and 1.06 g/t gold. That is about 67,000 tonnes of antimony and 222,000 ounces of gold, from SLR Consulting's NI 43-101 report dated 22 May 2026. The report draws on 53 diamond drill holes totalling 7,167 metres and 202 metres of underground chip sampling. The company's release sets no construction or production timetable.
Date | Event | Status |
|---|---|---|
28 May 2026 | Ministry of the Environment cancels the exploration licence after an unscheduled review | Annulled |
12 June 2026 | Military Metals files its appeal | Succeeded |
2 October 2026 | Company receives the Ministry's decision annulling the cancellation and reinstating the licence to 18 October 2026 | Announced on 19 October |
19 October 2026 | Company announces a four-year extension to 18 October 2030 | In force |
Six milestones to watch:
Mining authorisation. Military Metals has opened discussions with Slovakia's Ministry of Economy on the path from exploration to a mining and production authorisation. The Ministry of the Environment says mining would need an environmental assessment and separate approvals.
Local support. The company will set up a local advisory board, engage neighbouring municipalities, contribute to wastewater improvements and work with the Technical University of Košice.
Technical work. No programme or timetable is announced. An economic study, metallurgical results and an upgrade of the inferred resource would show the project maturing.
Funding. The release does not say how the next stage will be paid for.
EU talks. Executive Chairman Thomas Hüser and the company's Slovak general manager, Juraj Haruštiak, have opened discussions with EU representatives on Trojárová's contribution to the Critical Raw Materials Act's objectives.
The EU calendar. A new call for strategic projects is due towards the end of 2026, and the lists of critical and strategic materials are due for review by 24 May 2027.
Trojárová is the kind of project that could give the case for strategic status a concrete example. Antimony is on the EU's critical raw materials list but not its strategic one, and the Critical Raw Materials Act recognises strategic projects only for strategic materials, so Trojárová cannot be designated one today. If antimony were added at the 2027 review, a drilled European resource with a licence to 2030 would be an early candidate. This year's cancellation and reversal also illustrate the lead-time friction that the Act's third test, difficulty of increasing production, is meant to capture. It would be a candidate, not a lever: the resource is inferred, there is no economic study, and the project is early for strategic selection.